|
GBS Gold Tom's Gully Upgrade
Tom's Gully gold mine was purchased by GBS Gold in the third quarter of 2007. The mine ceased operation in March 2007 due to severe flooding. Following the acquisition of Tom’s Gully, GBS have invested in the renewal of the mine, with the aim of bringing it back into production.
Altus’s role in the re-commissioning is to provide engineering and drafting support in the following areas:
|
|
|
- Footing and slab design for the vertical mill
- Design of the monorail structure for the vertical mill
- Pipe rack design
- Cyclone structure design
- Design of the Lime area including tank design and silo and lime mill footings
- Modification of the Cyanide building to conform with current safety regulations
|
|


|